RoofCampus gutters — 328 linear metres, EPDM
Scope328 LM gutters treated with EPDM system
SystemEPDM gutter waterproofing — see gutter method
WarrantyDocumented 5-year warranty


01
Problem & Diagnosis
Campus gutter infrastructure across the Al Ain University blocks showed late-stage failure (lining fatigue, joint leaks, standing water) timed awkwardly against term dates; full works needed a calendar window.
02
Solution — Method
Make-safe containment first where active leaks ran; the full EPDM gutter treatment (328 linear metres) was completed in the break window, line by line with verification per run.
03
Result & Warranty
The campus entered the season with a verified gutter network; logistics and phasing followed the education protocol on ../../waterproofing-for-schools-universities/ this page.
Scope and key metrics for this project are recorded in the handover file and confirmed with the client.